This was an informational meeting called by Jasun Blocher to
settle the dispute of plastic or concrete pipes for the Storm Water
Project. There was also discussion about which contractor to use.
Joe Tierney and Jessica from GRW talked about their concerns on the
plastic piping. It was determined that INDOT approved plastic will
be used.
Linda Baker was given authority to sign the contract upon release of
funds with the lowest bidder on plastic. Gale Owens made the motion
to accept. Linda Baker seconded. Motion carried.
A pre-construction meeting will be held with construction to begin
approximately 150 days later.